In order to bid for a nonstandard construction job, an engineer needs to estimate the duration, D, of the project. Since no prior information on similar jobs is available, the engineer estimates that it may take 10 to 20 days. Suppose the PDF of D can be defined by a uniform distribution between 10 and 20 days.