The PlySide Shop wants to develop a cost estimating equation for its monthly cost of water. It has the following data:
Month Cost of Water (Y) Direct Labor-Hours (X)
March $26,000 3.000
June $30,000 3.400
September $34,000 4,000
December $29,000 3.200
What would be the best equation using the high-low method?