Best Builders constructed a new subdivision during 2014 and 2015 under contract with Town Stadium Co. Relevant data are summarized below:
contract amount 4.4

cost 2014 1.6

cost 2015 .8

billings 2014 2

billings 2015 2.4

Best uses recognizes revenue over time for this contract.

What is the journal entry in 2015 to record revenue