Based on the table below, perform resource leveling. Assume that each task can be performed independently of the other tasks. What is the completion date for the project after resource leveling? Please present your answer using the table format used in the text, showing before and after.
Task Workers Needed Scheduled Day(s)
1 3 1, 2, 3
2 2 2,3,4,5
3 2 2, 3, 4
4 1 5, 6, 7
5 3 7, 8, 9
6 2 10