Shoreline Stadium Case
The G&E Company is preparing a bid to build the new 47,000-seat Shoreline baseball stadium. The construction must start on July 3, 2017, and be completed in time for the start of the 2020 season. A penalty clause of $250,000 per day of delay beyond April 3 is written into the contract.
Percival Young, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $3 million on the project.
He also said if they were successful, the prospects of future projects are bright since there is a projected renaissance in building classic ball parks with modern luxury boxes.
ASSIGNMENT
Given the information provided in Table 6.3, construct a network schedule for the stadium project and answer the following questions
ID |
Activity |
Duration |
Predecessor(S) |
1 |
Baseball Stadium |
|
|
2 |
clear stadium site |
70 days |
- |
3 |
Demolish building |
30 days |
2 |
4 |
Set up construction site |
20 days |
3 |
5 |
Drive Support piling |
120 days |
4 |
6 |
pour lower concrete bowl |
120 days |
5 |
7 |
pour main concourse |
120 days |
6 |
8 |
Install playing field |
90 days |
6 |
9 |
Construct upper steel bowl |
120 days |
6 |
10 |
Install Seats |
140 days |
9 |
11 |
Build Luxury Boxes |
90 days |
9 |
12 |
Install jumbotron |
3o days |
9 |
13 |
Stadium Infrastructure |
120 days |
9 |
14 |
Construct Steel Company |
75 days |
10 |
15 |
Light installation |
30 days |
10 |
16 |
Build roof supports |
90 days |
4 |
17 |
Construct roof |
180 days |
16 |
18 |
Install roof Tracks |
90 days |
14 |
19 |
Install roof |
90 days |
17, 18 |
|
|
|
|
20 |
Inspection |
20 days |
8, 11, 13, 15, 19 |
1. Will the project be able to be completed by the April 3 deadline? How long will it take?
2. What is the critical path for the project?
3. Based on the schedule would you recommend that G&E pursue this contact? Why? Include a one-page Gantt chart for the stadium schedule.