A government agency is planning a new office building close to its current headquarters. Four proposed sites are to be evaluated. Any of these sites will save the agency $700,000 per year, since two of its current satellite offices will no longer need to be rented. The agency uses a 6% interest rate and assumes that the building and its benefits will last for 40 years. Based on a benefit-cost analysis what should the agency do?