Base course aggregate has a target dry density of 1197 lbcu


Base course aggregate has a target dry density of 119.7 lb/cu ft in place. It will be laid down and compacted in a rectangular street repair area of 2000 ft*48ft*6in. the aggregate in the stockpile contains 3.1 percent moisture. If the required compaction is 95 percent of the target, how many tons of aggregate will be needed?