Base course aggregate has a target dry density of 1197 lbcu


Base course aggregate has a target dry density of 119.7 lb/cu ft in place. It will be laid down and compacted in a rectangular street repair area of 2000 ft*48ft*6in. the aggregate in the stockpile contains 3.1 percent moisture. If the required compaction is 95 percent of the target, how many tons of aggregate will be needed?

Request for Solution File

Ask an Expert for Answer!!
Civil Engineering: Base course aggregate has a target dry density of 1197 lbcu
Reference No:- TGS0659476

Expected delivery within 24 Hours