Base course aggregate has a target dry density of 119.7 Ib/cu ft in place. It will be laid down and compacted in a rectangular street repair area of 2000 ft by 48 ft by 6 in. The aggregate in the stockpile contains 3.1 percent moisture. If the required compaction is 95% of the target, how many tons of aggregate will be needed?