You’re creating a customer database for the Winston-Salem Warthogs minor league baseball team. Make a project network given the information below. Complete the backward and forward pass, calculate activity slack, and recognize the critical path.
How long will this project take? How sensitive is network schedule? Compute the free slack and total slack for all noncritical activities.