A project team is studying the downtime cost of a soft drink bottling line. Data analysis in thousands of dollars for a three-month period is: Back-Pressure Regulator, 30; Adjust Feed Worn, 15; Jam Copper Head, 6; Lost Cooling, 52; Valve Replacement, 8; and Other, 5. Construct a Pareto diagram with a cumulative percent line.