Given the operation times provided:
Develop a sequence that minimizes the idle time at the two work centers. Assume you have constructed a chart of the activities at the two centers.
a. At what time will all of the jobs be done processing at Center 1?
b. At what time will all of the jobs be done processing at Center 2?
c. Determine each center's idle time, assuming no other activities are involved.
Job Times (minutes)
A B C D E F
Center 1 31 31 29 34 30 24
Center 2 23 30 27 34 25 22