The cost to do 100% inspection of incoming parts is $0.70 per item and the cost to replace a defect later in the process when the defect becomes obvious is $18.25.
At what proportion of actual defects is the the organization indifferent between 100% inspection, and accepting the lot and replacing the items later in the process?
Express as a decimal rounded to three places.