At what level of pretax cost savings would you be


Your firm is contemplating the purchase of a new $703,000 computer-based order entry system. The system will be depreciated straight-line to zero over its 5-year life. It will be worth $68,400 at the end of that time. You will be able to reduce working capital by $95,000 (this is a one-time reduction). The tax rate is 31 percent and your required return on the project is 19 percent and your pretax cost savings are $293,150 per year. what is the NPV of the project? What is the NPV if the pretax cost savings are $211,050 per year? At what level of pretax cost savings would you be indifferent between accepting the project and not accepting it?

Request for Solution File

Ask an Expert for Answer!!
Finance Basics: At what level of pretax cost savings would you be