At 10000 direct labor hours the line drawn from the total


1. Cali Company has prepared a graph of flexible budget data. At zero direct labor hours, the total budgeted cost line intersects the vertical axis at $20,000. At 10,000 direct labor hours, the line drawn from the total budgeted cost line intersects the vertical axis at $85,000. How may the fixed and variable costs be expressed?

2. The flexible budget formula is fixed costs $50,000 plus variable costs of $4 per direct labor hour. What is the total budgeted cost at (a) 9,000 hours and (b) 12,345 hours?