1. Develop a summary bar chart for the activities listed in the table below.
2. Assuming the cost to operate each activity run at a linear rate, calculate the cost per day to run the project.
3. Plot the cost versus time cumulative curve (S curve) for this project. Reference page 230 in the text.
Activity List for a small Commercial Building Project
Activity
|
Duration
|
Cost
|
Predecessor
|
Foundations and slab utilities
|
6
|
12,500
|
none
|
Structural Steel
|
4
|
23,000
|
Fnds & Slab
|
Roof Deck
|
4
|
10,000
|
Structural Steel
|
Floor Slab
|
2
|
5,500
|
Fnds & Slab
|
Siding
|
6
|
19,000
|
Structural Steel
|
Windows and Doors
|
2
|
4,700
|
Siding
|
Mechanical
|
14
|
16,800
|
Roof Deck
|
Electrical
|
14
|
15,700
|
Roof Deck
|
Insulation
|
4
|
8,800
|
Siding
|
Finishes
|
5
|
7,000
|
Insulation
|