MacHinery Manufacturing Company is considering a three-year project that has a cost of $75,000. The project will generate after-tax cash flows of $33,100 in Year 1, $31,500 in Year 2, and $31,200 in Year 3. Assume that the appropriate discount rate is 10% and that the firm's tax rate is 40%. What is the project's discounted payback period?