Question: 1. Calculate the fully loaded cost of labor for your Project Engineer using the following data:
Hourly rate: $40/hr
Estimated hours of work: 120
Overhead rate: 65%
Personal time: 15%
2. Assume that overhead is charged on a flat-rate basis. Each member of the project is assigned an overhead charge of $150/week. What would the fully loaded cost of labor be for an employee, given that she is assigned to the project for 200 hours at $10.50/hour?