Assume also that you can crash an activity down to 0 weeks


Assume that the activities in Problem 3.11 have the following costs to shorten: A, $300/week; B, $100/week; C, $200/ week; E, $100/week; and F, $400/week. Assume also that you can crash an activity down to 0 weeks in duration and that every week you can shorten the project is worth $250 to you. What activities would you crash? What is the total crashing cost?