Assume a firm works on a set large scale development


Assume a firm works on a set large scale development projects, in which the learning curve theory can be utilized. The first project takes 200 days and the second project takes 180 days. Which of the following statements is correct

A - The third project takes 160 days

B - The fourth project takes 145.8 days

C - The fifth project takes 162 days

D - The eight project takes 131.2 days

E - None of them is correct

 

 

Request for Solution File

Ask an Expert for Answer!!
Project Management: Assume a firm works on a set large scale development
Reference No:- TGS01088920

Expected delivery within 24 Hours