Assign tasks according to the greatest positional weight


A shop works a 400 minute day. The manager of the shop wants an output of 200 units per day for the assembly line that has the elemental tasks shown in the table. Do the following:

a. Construct the precedence diagram.
b. Assign tasks according to the most following tasks rule. Break ties with the greatest positional weight rule.
c. Assign tasks according to the greatest positional weight rule. Break ties with the most following tasks rule.
d. Compute the balance delay for each rule. Which one yields the better set of assignments in thisinstance?

Solution Preview :

Prepared by a verified Expert
Operation Management: Assign tasks according to the greatest positional weight
Reference No:- TGS01215928

Now Priced at $15 (50% Discount)

Recommended (96%)

Rated (4.8/5)