Question: The data below was collected for an assembly line balancing analysis. what additional data is needed for the analysis?
work element element time
mold 13
cut 3
shape 6
fasten 5
treat 10
a - historical employee efficiency rates
b - balance delay rate
c - number of workstations
d - precedence information