As a production manager, you have received an order for product A that needs two subassemblies and two units of component B. The order is for 1000 units of Product A.
The first subassembly consists of a frame, two supports, and a handle. The second subassembly consists of a hub and five blades.
The following table gives lead times, on-hand inventory, and scheduled receipts.
a) Construct a product structure.
b) Construct a time-phased product structure
c) Prepare a net material requirements plan