Articulate an integer program for following table
Hagger Engineering Corporation is considering undertaking numerous proposed projects for the next fiscal year. The projects the number of engineers as well as the number of support personnel required for each project as well as the expected profits for each project are summarized in the following table:
|
Project
|
|
1
|
2
|
3
|
4
|
5
|
6
|
Engineers Required
|
20
|
55
|
47
|
38
|
90
|
63
|
Support Personnel Required
|
15
|
45
|
50
|
40
|
70
|
70
|
Profit (million $)
|
2.0
|
3.6
|
4.0
|
3.0
|
7.2
|
4.4
|
Articulate an integer program that maximizes Hagger's profit subject to the following management constraints-
(a) Define variables
(b) Use no more than 175 engineers
(c) Use no more than 150 support personnel
(d) If either project 6 or project 4 is done both must be done
(e) Project 2 can be done merely if project 1 is done
(f) If project 5 is done project 3 mustn't be done and vice versa
(g) No more than three projects are to be done.