Question: Justine's Needle is a tailor shop handling a wide variety of repairs and alterations. Justine claims that on an average day, she receives 23.1 new jobs and that the theoretical flow time for a job is 0.8 days. On an average day, there are 31.2 jobs in some stage of the process at her shop. Are these numbers consistent?