Approximate probability that the project


A given project's expected duration along its critical path is 25 days. Management wants to know the probability that the project will finish in 22 days or less. The variance along the project's critical path has been calculated to be 6.02778 days. Thus, what is the approximate probability that the project will finish in 22 days or less:

0.06

0.11

0.43

0.61