Applying the pert method


Question 1: A project is programmed below. The numbers in the circles are the expected completion time in days.

1741_applyying pert method.jpg

Required:

a) Recognize the main steps in applying the PERT method.

b) Set out the conditions which must be satisfied for the PERT to be applicable.

c) Calculate the earliest expected starting time and the earliest expected finishing time for each activity.

d) What do you mean by critical path?

e) If the project must be done in 21 days, what is the total slack or ‘safety factor’?

f) Find out the total slack in (i) activity d and (ii) in activity c?

g) Determine the free slack in (i) activity a and (ii) activity b?

Request for Solution File

Ask an Expert for Answer!!
Operation Research: Applying the pert method
Reference No:- TGS06111

Expected delivery within 24 Hours