The Owens Company uses the machine hour method of applying factory overhead to production. The budgeted factory overhead last year was $200,000, and there were 40,000 machine hours budgeted. Job 84 was started and completed during the period. Direct materials costing $900 were incurred. Twenty-five direct labor hours were worked at a cost of $350, and 40 machine hours were incurred. What was the cost of Job 84?