Question1. What are the phases of Project Management?
Question2. Differentiate between PERT and CPM.
Question3. Explain how the network PERT/CPM can help in managing operations.
Question4. What are the applications of Network Techniques?
Question5. A project consists of 7 activities as in the table below:
(i) Draw the project network?
(ii) What is the normal project duration?
(iii) List the activities falling on critical path.
(iv) Calculate the total cost slope falling along the critical path.