Question1. What are the phases of Project Management?

Question2. Differentiate between PERT and CPM.

Question3. Explain how the network PERT/CPM can help in managing operations.    

Question4. What are the applications of Network Techniques?

Question5. A project consists of 7 activities as in the table below:

2407_ac ti vity table.jpg

(i) Draw the project network?

(ii) What is the normal project duration?

(iii) List the activities falling on critical path.

(iv) Calculate the total cost slope falling along the critical path.

 