Annie is planning a large surprise party for her sister Gwendolyn. She has developed the plan below, including estimates of the time (in hours) and cost necessary to perform each of the activities required at the currently planned pace and at the crashed pace.

 

Activity

Predecessor

Current Planned Duration (hours)

Minimum Crash Duration (hours)

CurrentPlanned Cost

TotalCost if Crashed

A. Create Guest List

-

8

4

$200

$310

B. Send Invitations

A

2

1

$125

$150

C. Buy Decorations

A

8

6

$300

$370

D. Plan Menu

A

3

2

$150

$210

E. Purchase Food

D

4

2

$475

$550

F. Prepare Food

E

5

3

$225

$475

a. Annie is most interested in reducing the time associated with creating the guest list. What is the crash cost per hour for that activity?

b. Annie will save $40 for every hour she can reduce from her plan. Annie has decided to crash her project and use the money she saves to purchase a larger gift for Gwendolyn. Which activity should she crash first?

c. Annie has now crashed activity A by four hours at a cost of $110. What other activity could she crash to further reduce the project?

d. Annie has now crashed activity A by four hours at a cost of $110 and activity E by two hours at a cost of $75. What other activity could she crash to further reduce the project?

e. How much money did Annie save by crashing the project?

f. What is the duration of the fully crashed project?

Solution Preview :

Prepared by a verified Expert
Operation Management: Annie is most interested in reducing the time associated
Reference No:- TGS01188427

Now Priced at $40 (50% Discount)

Recommended (95%)

Rated (4.7/5)

A

Anonymous user

3/22/2016 8:05:43 AM

Consider the case scenario and all its facts, information and table and on the basis of this information, you have to answer the following questions. Please prepare the paper by following the APA instructions. 1) Annie is most interested in decreasing the time related with creating the guest list. Determine the crash cost per hour for that action? 2) Annie will save $40 for each and every hour she can decrease from her plan. Annie has decided to crash her project and make use of the money she saves to buy a big gift for Gwendolyn. Name the activity which must she crash first? 3) Annie currently crashed activity A by 4 hours at a cost of $110. What other activity could she crash to additionally diminish the project? 4) Illustrate how much money did Annie save via crashing the project? 5) Determine the duration of the completely crashed project?