Anna works on an assembly line where it takes her 55


Anna works on an assembly line where it takes her 55 minutes to produce 30 units of a product needed to fill a container. It takes her an additional 5 minutes to transport the container to Josh, who works at the next station. The current assembly line uses 8 kanbans between Anna's and Josh's stations. Compute the demand for the product per minute and per hour.

Help this homework with Excel please.