Ann Chovies, owner of the Perfect Pasta Pizza Parlor, uses 20 pounds of pepperoni each day in preparing pizzas. Order costs for pepperoni are $10.00 per order, and carrying costs are 4 cents per pound per day. Lead time for each order is 3 days, and the pepperoni itself costs $3.00 per pound.If she were to order 80 pounds of pepperoni at a time, what would be the length of an order cycle?
5 days
0.25 days
3 days
4 days
0 days