Analysts at your firm are examining a project with uncertain cash flows. There is a 10% chance the project will yield an NPV of $9,300, a 60% chance the project will yield an NPV of $13,600, a 20% chance the project will yield an NPV of 1$5,300, and a 10% change the project will yield an NPV of $22,300.
What is the Expected NPV of this project?