Response to the following problem:
Fornelli, Inc. can produce 100 units of a component part with the following costs:
Direct materials $15000
Direct labor 6500
Variable overhead 16000
Fixed overhead 11000
If Fornelli, Inc. can purchase the component part externally for $44000 and only $4000 of the fixed costs can be avoided, what is the correct make-or-buy decision?