An assembly line has the following tasks (times shown in minutes).
a. Six assemblies are required per hour. Balance the line (Tips: Calculate required cycle time and theoretical work stations.)
b. What is the efficiency of the line?
c. Balance the line if task e has a time of 1 minute instead of 3. After rebalance, what is the efficiency of the line?