An assembly line has 5 operations with total work content


An assembly line has 5 operations with total work content of 5.62 min. The demand is 30 units/8hour shift. What is the theoretical minimum number of workers required on this line?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: An assembly line has 5 operations with total work content
Reference No:- TGS0571230