An architect has five projects to complete. She estimates that three of the projects will require 1 week to complete and the other two will require 3 weeks and 4 weeks. During the time these projects are completed, assume no other projects are worked on during this time.
What is the architect’s flow rate? projects per week
(Round your answer to 1 decimal place.)