An analyst has timed a metal-cutting operation for 50


An analyst has timed a metal-cutting operation for 50 cycles.

The average time per cycle was 10.40 minutes, and the standard deviation was 1.20 minutes for a worker with a performance rating of 125 percent.

Assume an allowance of 16 percent of job time. Find the standard time for this operation.