Activity-Based Costing
An alternate method of assigning costs is activity-based costing. The major activity for the production of both Processor01 and Android01 is component assembly. There will be a total of 125,000 assemblies per year for the production of 500 units of Processor01 and 300 units of Android01 at a total cost of $25 million. Each unit of Android01 will require 180 assemblies. The remaining cost for the production of Android01 is for components, at $25,000 per unit.
Question: What would be the cost per unit of producing Android01 using activity-based costing?
Submit your Activity-Based Costing Report and Calculations to the dropbox below. Be sure to show your calculations in Excel and provide a narrative analysis in PowerPoint. Your narrative analysis should summarize the results of your analysis and make recommendations for the benefit of company.