An aircraft company has an order to refurbish the interiors of six jet aircraft. The work has a learning curve percentage of 85. On the basis of previous experience with similar jobs, the industrial engineering department estimates that the first plane will require 280 hours to refurbish. Estimate the amount of time that will be needed to complete: a) The second plane b) The fifth plane c) All six planes.