At the beginning of the year, Monroe Company estimates annual overhead costs to be $800,000 and that 200,000 machine hours will be operated. Using machine hours as a base, the amount of overhead applied during the year if actual machine hours for the year was 150,000 hours is:
A) $800,000.
B) $200,000.
C) $600,000.
D) $37,500.