Altman Distribution fills catalog orders. Samples of size n = 100 have been taken each day over the past 6 weeks. The average defect rate was .05.
Calculate the standard deviation of the sampling distribution
Calculate the upper control limit for a P chart, using z=3. State your answer to four decimal places.
Calculate the lower control limit for a P chart using z=3. State your answer to four decimal places.