Although not essential it is common practice when procuring


Task 01

"Although not essential, it is common practice when procuring a building to appoint the contractor on a standard-form building contract."(Murdoch J and Hughes W (2008) p101).

But some parties, particularly in housing construction market, use ad-hoc contracts which are prepared based on their own terms to suite their own needs.

JCT, NCE, FIDIC, ICTAD are examples of standard-form of contracts.

Discuss why standard-form contracts should be preferred over ad-hoc contracts.

Task 02

ABC Construction Ltd receives a letter from XY Developers:

Re: The Design and Construction of XY Homes

We refer to your tender dated 7th June 2014 regarding the construction of XY Homes. As per the decision taken by our board of directors, it is our intention to award carrying out of subject works to you. However, as certain decisions still pending with the board regarding Employer Supply Materials, further negotiations will be carried out in order to agree the final contract price. You are instructed to mobilize immediately as timely completion is paramount. Please be informed that the damages for delay will be  Pounds 50 per day.

Yours faithfully

Richard Butler

Chief Executive

XY Homes

ABC Construction Ltd started mobilizing and made arrangements by sending purchase orders to material suppliers and letter of intents to sub-contractors. When ABC Construction Ltd requested the advance payment be paid, XY Homes refused claiming there was no contract existing.

Analyse the situation and advise ABC Construction Ltd.

Task 03

Once parties enter in to a contract they need to identify precisely what obligations it imposes on them. For that they need to understand the terms it includes. There are three types of contractual terms included in contracts:

i. express terms which are contained in the main contractual document itself

ii. those (also express terms) contained in other documents to which the main contract document refers

iii. terms which are implied by law

iv. legal liability under the law of tort.

Explain the main obligations that construction contracts impose on parties with reference to above different types of terms and the liability.

Task 04

Part II of the Housing Grants, Construction and Regeneration Act 1996defines 'construction contract' as any agreement in writing, or evidenced in writing, under which a party does any of the following:

  • Carries out construction operations.
  • Arranges for others to carry out construction operations (for example through sub-contracts).
  • Provides labour for the carrying out of construction operations.

Most of the standard forms of Construction Contracts include the following documents;

i. Articles of Agreement

ii. Particular and General Conditions

iii. Specifications

iv. Drawings

v. Bills of Quantities

vi. Schedules.

Explain the significance of above documents with reference to the definition of 'construction contract' in Part II of the Housing Grants, Construction and Regeneration Act 1996.

Task 05

"It is well known that The Contracts (Rights of Third Parties) Act 1999 grantees the third party's rights unlike earlier days. In the meantime several requirements have to be fulfilled in the contract and therefor the application is limited. Under the construction contract the customers may sue the contractor directly along with seller of the building. It is necessary to ensure the third party's right under the construction contract in terms of ensuring quality and sound construction. In the meantime is criticized there is no useof the above Act where the Act cannot be applied if its jurisdiction has not been recognized in the contract and the restrictions imposed in the Act.It could be criticized that still there is no development in law for the protection of the third party's rights".

Critically examine the provisions of The Contracts (Rights of Third Parties) Act 1999 and comment its application in the construction contract.

a) FIDIC Standard Form of International Construction Contract (the Red book 1999)

b) JCT Standard Form of Building Contract Private Edition with Quantities  2011

Request for Solution File

Ask an Expert for Answer!!
Business Law and Ethics: Although not essential it is common practice when procuring
Reference No:- TGS01243276

Expected delivery within 24 Hours