The Manassas Company has 55 obsolete keyboards that are carried in inventory at a cost of 9600. If these keyboards are upgraded at a cost of 7700, they could be sold for 19300. Alternatively, the keyboards could be sold "as is " for 7300. What is the net advantage or disadvantage of re-working the keyboards?