A project has an initial requirement of $234,703 for new equipment and $12,219 for net working capital. The fixed assets will be depreciated to a zero book value over the 3-year life of the project and have an estimated salvage value of $108,009. All of the net working capital will be recouped at the end of the project. The annual operating cash flow is $68,463 and the cost of capital is 6% What is the project's NPV if the tax rate is 38%?