1. If an interim deliverable is too late for the next successor deliverable, the best way for a project team to adjust the schedule to finish earlier is by:
a. Increasing resources.
b. Reworking the critical path.
c. Decreasing the project scope.
d. Creating concurrent deliverables.
e. Negotiating deadlines with the project customer and/or project sponsor.
2. All of the following focus on improving quality through process control EXCEPT:
a. DMAIC
b. Poka-Yoke
c. Six Sigma
d. Taguchi method
e. Toyota Production System
3. Guidelines of good ground rules for project team meetings do all of the following EXCEPT:
a. Address difficulties that often arise in meetings.
b. Are achievable, realistic, and revised as needed.
c. Improve the project team’s effectiveness and efficiency.
d. Are inclusive, covering a wide range of potential problems.
e. Minimize misunderstandings, disruptions, and protracted disputes.