The following jobs are waiting to be processed at Julie Morel's machine center

In what sequence would the jobs be ranked according to the following rules:
(a) FCFS,
(b) EDD,
(c) SPT, and
(d) LPT?
All dates are according to shop calendar days. Today on the planning calendar is day 130, and none of the jobs have been started or scheduled. Which rule is best?