After planning to build a new plant kallisto backpack


After planning to build a new plant, Kallisto Backpack Manufacturing purchased a large lot on which a small building was located. The negotiated purchase price for this real estate was $1,800,000 for the lot plus $600,000 for the building. The company paid $87,000 to have the old building torn down and $117,000 for levelling the lot. Finally, it paid $3,480,000 in construction costs, which included the cost of a new building plus $227,000 for lighting and paving a parking lot next to the building.

Present a single journal entry to record the costs incurred by Kallisto, all of which were paid in cash (assume a date of March 10, 2017, for your entry).(If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)