Question - Adtack Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below:
Job #359 Job #360 Job #361
beginning work in process ..... $3,500 $6,300 $4,800
COSTS ADDED DURING MARCH
direct materials .............. $4,600 $3,300 $4,900
direct labor .................. 3,000 4,000 5,000
Madtack applies overhead to jobs at a rate of 125% of direct labor cost. During March, Madtack completed and sold Job #360. Job #361 was also completed but was not sold by the end of March. Job #359 was not completed by the end of March.
Madtack's actual overhead cost for the month of March totaled $18,000.
Calculate Madtack's cost of goods manufactured for March. Do not use decimals in your answer.