Question: While managing a project using a hybrid approach, the project manager realizes that there is a high level of rework due to quality issues. Because of that, each feature is taking longer than initially estimated What should the project manager do to address the issue? • Address the issue during the next sprint planning meeting. • Extend the dates for future project milestones • Escalate the issue to the project sponsor. • Initiate a change request to extend the project end date.